Energoprojekt Oprema wins EUR 4.2 million contracts for projects in Serbia



This company inked a contract with the Elektromreze Srbije public company to build the 400kV long-distance power line Beograd 8 - Pancevo 2. The total value of this project is EUR 3.48 million. It is to be implemented in 18 months.
Energoprojekt Oprema also signed contracts with Elektrovojvodina to supply a 110/21/10.5 kV power transformer with an apparent power of 31.5/31.5/10.5 MVA for two substations (Srbobran and Rimski Sancevi), one for each. This EUR 718,000 worth of project is to be completed in 240/360 days.


